Skip to content
Home
Who Are We
What We Do
Dams
Pipe Lines – Steel
Pipe Lines – HDPE
How We Do It
Underwater Drone
Projects
Majuba Power Station
Ingula PSS – Bramhoek Dam
Ingula PSS – Bedford Dam
Spring Grove Dam
Nacala Dam
Neckartal Dam
Neckartal Pump Station
Kudube Dam
Von Bach Dam
Orange Farm
Exarro Belfast Bip
Rustenburg Municipality
Thune Dam
Jozini Dam
Contact Us
Home
Who Are We
What We Do
Dams
Pipe Lines – Steel
Pipe Lines – HDPE
How We Do It
Underwater Drone
Projects
Majuba Power Station
Ingula PSS – Bramhoek Dam
Ingula PSS – Bedford Dam
Spring Grove Dam
Nacala Dam
Neckartal Dam
Neckartal Pump Station
Kudube Dam
Von Bach Dam
Orange Farm
Exarro Belfast Bip
Rustenburg Municipality
Thune Dam
Jozini Dam
Contact Us
Exarro Belfast Bip
Projects
Exarro
Belfast Bip
Installation of approx. 38km HDPE pipe lines
Main contractor:
Concor
Duration:
1 Year
Cost:
R19 Million
Equipment:
HDPE pipes from 25 mm to 355 mm.
Pressure ratings from PN4 to PN16.
Various steel sections.
Valves.
Flow meters.
Hydro pressure testing of all pipe lines up to 24Bar.